Impact

Priority and Funding

  • This project is classified as a normal project 

  • This is a sponsor funded project from Accommodation Catering and Events  

 

Impact and Dependencies

This project will require strong representation across the business, IS and input from Core Systems Finance Team technical representative 

The business have advised that as significant market research has been undertaken by the Business Lead and the ACE Technical Lead,  there is a  full awareness of the business requirements and so in this instance a business analyst would not be required 

 

Project Risks

Ref Title Description Impact Probability RAG Owner Management Approach
1 Unable to source 3 quotes for comparison Having undertaken market-research, it is not possible to source 3 solutions that meet requirements - and subsequently 3 quotes  Moderate Low Green Ian Macaulay Retain
2 Supplier Purchase in excess of £50,000 A potential solution exceeds the £50,000 threshold for 3 quotes  Major Low Green Ian Macaulay Retain
3 Insufficient budget (monetary) available to procure a solution Preferred solution may exceed the available budget for purchase  Major  Low Green Ian Macaulay Retain
4 No suitable solution determined  Having completed the initial market-research, no potential solutions have been located  Major Low Green Ian Macaulay Retain
5 Insufficient project budget to complete the project The effort from IS required to complete the exceeds the current approved budget  Moderate Medium Green Ian Macaulay Retain
6 Unavailability of the project manager  Due to unforeseen circumstances, the project manager is not available to work on the project Major  Low Green Emma McNab Retain
7 Unavailability of the business lead Due to unforeseen circumstances, the business lead  is not available to work on the project Major Low Green Ian Macaulay Retain
8 Unavailability of IS personnel Due to unforeseen circumstances, some of the IS technical resource are not available to work on the project Major  Low Green Paul McNulty  Retain
9 Procurement processes are not followed The University of Edinburgh guidelines are not followed during the procurement process Major Low Green Ian Macaulay Retain 
10

Integration with Finance unconfirmed

There is a risk that by the time the project is ready to issue the ITQ, the requirements and method to integrate with the Core Finance system have not been fully defined.  Major Medium Amber Ian Macaulay Avoid
11

Core Systems Finance team not fully engaged

Due to the workload of individuals within the Core Finance system team, it may not be possible for them to fully engage with the project in detailing the system integration requirements. Major Medium Amber Ian Macaulay Avoid

 

Project Info

Project
Delivered Catering Procurement
Code
ACS042
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Ian Macaulay
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
30-Aug-2019
Planning Date
20-Sep-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation

Plan