Organisation

Work/Task Breakdown

Project Planning Phase 

Task Who Priority When 
Produce Project Brief Project Manager Must  
Produce Project Plan  Project Manager  Must  
Produce Project Estimate Project Manager Must  

O1. Specify Business Requirements 

Task Who Priority When 
D1.1 Document Business Requirements       
D1.1.1 Define the business requirements required for the new Delivered Catering solution, ensuring each requirement is classified according to MoSCoW Business Lead Must  
D1.1.2 Consult with Core Finance System to ensure process integration  ACE Technical Lead Must  

O2. Complete Relevant GDPR Checks 

Task Who Priority When 
D2.1 Produce a Data Protection Impact Assessment      
D2.1.1 Complete a DPIA and verify with DPO Project Team  Must  

O3. Undertake Procurement Process

Task Who Priority When
D3.1 Prepare ITQ       
D3.1.1 Prepare Invitation to Quote (ITQ) Document  Business Lead  Must  
D3.1.2 Prepare Procurement brief incorporating; aspects such as business and technical requirements; selection criteria; Award Criteria  Business Lead  Must  

D3.1.3 Create a Procurement log to incorporate  all aspects of the procurement; namely;

  • Invitation to Quote (ITQ) 

  • Specification of requirements  

  • UoE terms and conditions  

  •  A template to record quotes received 

  • Area too record copy of purchase Order 

  • Area to record decision justification and relevant correspondence 

Project Manager  Must  
D3.2 Market Research      
D3.2.1 Complete initial market research of potential suppliers Business Lead  Must  
D3.3 Issue ITQ      

D3.3.1 Prepare shortlist of potential suppliers to receive ITQ

Business Lead Must  
D3.3.2 Issue ITQ      
D3.4 Review Supplier Responses      
D3.4.1  Review and evaluate supplier responses  Project Team Must  
D3.4.2 Arrange supplier demonstrations (including Accessibility Reviews)  Project Manager Must  

D3.4.3 Document Supplier Evaluation

Business Lead Must  
D3.4.4 Complete Consensus and determine preferred supplier Business Lead Must  

O4. Award Contract 

Task Who Priority When
D4.1 Complete Procurement      
D4.1.1 Confirm terms and conditions Project Sponsor Must  
D4.1.2 Raise Purchase Order  Project Sponsor Must   
D4.1.3 Complete IS procurement Checklist Project Manager Must  

Project Closure  

Task Who Priority When 
Prepare and circulate project closure report  Project Manager Must  
Close Project      

Resources, Skills and Costs

During the procurement process, the ACE technical Lead will lead the IT Procurement questions with assistance from colleagues in both Applications Directorate and Information Security 

Department Role Estimated (Cost (days)
Accommodation Catering and Events Business Lead   
  ACE Technical Lead   
  ACE Financial Accounts Lead   
Project Services Project Management  24
Development  IS Development Technology Lead  3
3 IS Software development Lead  3
Production Management  IS Applications Management 3
  IS technology Management 3
Information Security  Information Security Lead   
Core Finance System Core Finance System Solutions Architect  
  Contingency @10% 4

 

Project Governance

The project manager, Business Lead and ACE technical lead will meet the project sponsor on a monthly basis to; 

  • review progress in relation to the project plan and budget 

  • review any issues escalated from the project team 

  • review the project risk register 

  • confirm activities for the following period 

The project team will meet on a weekly basis to; 

  • review progress in relation to the project plan 

  • review any issues and agree actions 

  • confirm activities for the following week 

 

Project Stakeholders

Name  Business Area Role
Andrew Glass Accommodation Catering and Events ACE technical Lead (Project Team)
Andy Stewart  IS Applications Project Services Project Manager (Project Team)
Applications Management Lead  IS Applications Applications Management  Applications Management Lead 
Development Technology Lead  IS Applications Development Technology Development Technology Lead (Project Team)
Ian Macualay Accommodation Catering and Events Project Sponsor
Information Security Lead  Information Security Information Security Lead (Project Team)
Lorraine Hyslop Accommodation Catering and Events ACE Financial Accounts Lead (project Team)
Mike McMonagle Core Finance System Core Finance System Solutions Architect (Project Team)
Rae Conn Accommodation Catering and Events Business Lead (Project Team)
Software Development Lead IS Applications Development Software Development Lead (Project Team)
Technology Management Lead IS Applications Technology Management  Technology Management Lead (Project Team)

 

Project Estimations

The project estimate is also detailed within the Estimation Log 

 

Project Info

Project
Delivered Catering Procurement
Code
ACS042
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Ian Macaulay
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
30-Aug-2019
Planning Date
20-Sep-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation

Plan