Plan

Document Sign-off

 

Document Sign-off

Name Role Date signed off
  Project Sponsor  
  Project Manager  
  Programme Manager  
     
     

 

Governance

Project will all have these governance roles by default.

Priority and Funding

This has been initiated as a Priority 1 initiative. Funding is direct and from existing budgets for handling such projects. 

 

Background

The purpose of this project is to prioritise and migrate the Windows 2003 and 2008 server estate to Windows Server 2016 to a supported level by the end of 2020. In addition, the project will monitor the holistic estate in order to be ready to start planning the Windows Server 2012 to 2016 (or another Microsoft upgrade if available) in two years time.

Scope

The items designated as in scope for this project are detailed below:

 

* Prioritised Windows 2003 and 2008 servers in the first two years

Document Approvals

Name Project Role Date
Graeme Wood Project Sponsor (Head, ITI Enterprise Services) 28/02/2017
Kirsty Waddell ISG Project Manager 28/02/2017

Murray Dippie

Governance

Project will all have these governance roles by default.

Role Name Division / Group / Team / College / School and Title
Project Sponsor Graeme Wood

Enterprise Services Manager

Priority and Funding

This is a Priority 1 Director initiative with a Programme Prioritisation rating of 12. Funding is direct – Estates are holding a fund of £200K on behalf of the IT Infrastructure Division of ISG that was previously secured from the College of Science and Engineering. An additional £50K through a small capital grant project from Estates has also been identified.

 

Further funding of £250K is being requested from the Campus Sustainability Fund.

 

Background

 

The purpose of this project is to increase the resilience and efficiency of the datacentres at both the James Clerk Maxwell building at the King’s Buildings and the one in Appleton Tower, which is in the central area of the University. The plan is to improve both datacentres to a Tier 2 Uptime Institute Performance Standard, or as a minimum to improve operational resilience to an acceptable level which is similar to Tier 2.

 

Approval Record

 

Check List Item

Quality Criteria

Complete Y/N

Reviewed By

Category and Billing Arrangements

  • Category correctly assigned
  • Billing arrangements agreed with all parties