Revision History
|
Version |
Author |
Summary of Changes |
Date |
|
V0.1 |
During March,
- The focus this month, has been on the the Kx Infrastructure Upgrade project (ACS041) resulting in teh deployment of the Application Webservers into the live environment.
Forward Look

Resource Position

Section Two: Projects Not Started
Document Sign-off
|
Name |
Role |
Date Signed Off |
|
Maurice Franceschi |
During February,
During January,
- Work on the Kx Infrastructure project continues. the project is currently running around two weeks behind the original schedule due to unexpected technical issues encountered during the testing of Application Webservers via teh Load Balancers
- Initial project proposals have been received for the next Annual planning round. The programme manager will look to arrange an estimation meeting before the end of February
Discussions
It is strongly recommended that this template is developed as a Word document and once approved, transferred to this project page (due to the limitation of the website in regard to editing and for easier sharing, tracking and versioning)
project_planning_-_project_brief_template.docx
During December,
Document Sign-off
| Name | Project Role | Date Signed Off |
|---|---|---|
| Maurice Franceschi | Programme Manager | 18/02/19 |
|
David Fergusson |
Project Sponsor | 18/02/19 |
|
David Fergusson |
UoE Service Owner |
Document Sign-off
| Name | Project Role | Date Signed Off |
|---|---|---|
| Maurice Franceschi | Programme Manager | 10/12/2018 |
|
David Fergusson |
Project Sponsor | 23/01/2019 |
|
David Fergusson |
UoE Service Owner |
During November,
Current project activity - the main focus has been on the Kx Infrastructure Upgrades project. As a result of unexpected issues with the new primary Application Webserver during both the build and the subsequent user acceptance testing, the project is around 3 weeks behind schedule
Discussions
- regarding the project to host the ACE VOIP messaging server have concluded that this project should be managed under ITI
- regarding the strategy around the Delivered Catering procurement is on-going