Report for November 2018
- Report Date
- November 2018
During November,
Current project activity - the main focus has been on the Kx Infrastructure Upgrades project. As a result of unexpected issues with the new primary Application Webserver during both the build and the subsequent user acceptance testing, the project is around 3 weeks behind schedule
Discussions
- regarding the project to host the ACE VOIP messaging server have concluded that this project should be managed under ITI
- regarding the strategy around the Delivered Catering procurement is on-going
Forward Look


Resource Position


Section Two: Projects Not Started
The scheduled projects for 2018-19 are:
| Project Info | Programme Managers Commentary |
|
AP89-901 Salto Door Access Funded Planning: February 2019 Delivery: t.b.c.
|
Plan This project has been declared as part of the annual planning process for 2018-19 Dependencies: - On the availability of the ACE technical lead - will require input from IS Applications Development Technology and IS Applications Production Management |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||
|
Kx Infrastructure Consolidation Category: Discretionary Sponsor Funded
Milestones will require to be re-planned after the issues with the primary Application WebServer has been resolved
RAG Status: Amber |
Report by Andy Stewart for November 2018 Achievements in the last period
Issues
Next steps
RAG CommentaryThe project is currently running three weeks behind schedule due to the level of unexpected issues encountered with the new Application Webservers. The delay is not impacting on the business and the project will be re-planned |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 07/12/18 | 7 | Completion of Programme Activity within 2018-19 | Green | Andrew Stewart |
| 07/12/18 | 8 | Programme Management budget for 2018-19 being exceeded | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site