Report for December 2018
- Report Date
- December 2018
During December,
- Work on the Kx Infrastructure project continues. the project is currently running around four weeks behind schedule due to unexpected technical issues encountered during the build and testing of the primary Test Application Webserver
- Initial project proposals have been received for the next Annual planning round. The programme manager will look to arrange an estimation meeting before the end of January
- The Salto Door Access project has been deferred to Q3 2019 until the Network Replacement project is more advanced. As a result, the overall programme budget will now be reduced by 50 days to 112 days
Discussions
- Regarding the strategy around the Delivered Catering procurement is on-going
Forward Look



Resource Position



Section Two: Projects Not Started
The scheduled projects for 2018-19 are:
| Project Info | Programme Managers Commentary |
|
AP89-901 Salto Door Access Funded Planning: April 2020 Delivery: October 2020
|
Plan This project has been declared as part of the annual planning process for 2018-19, but has been deferred to Q3 2019 until the Network Replacement project is more advanced Dependencies: - On the availability of the ACE technical lead - will require input from IS Applications Development Technology and IS Applications Production Management |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||
|
Kx Infrastructure Consolidation Category: Discretionary Sponsor Funded
Milestones have been re-planned
RAG Status: Amber |
Report by Andy Stewart for December 2018 Achievements in the last period
Issues
Next steps
RAG CommentaryThe project has been re-planned due to the extended time to complete UAT on the test primary application server. This will result in a project extension of five weeks. The delay is not directly impacting on the business. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 08/01/19 | 7 | Completion of Programme Activity within 2018-19 | Green | Andrew Stewart |
| 07/12/18 | 8 | Programme Management budget for 2018-19 being exceeded | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site
| Attachment | Size |
|---|---|
| 34.17 KB | |
| 29.72 KB | |
| 25.71 KB | |
| 28.78 KB | |
| 20.87 KB | |
| 29.32 KB | |
| 21.22 KB |