Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 GREEN GREEN GREEN GREEN
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN
Report for August 2019 August 2019 GREEN GREEN GREEN GREEN

Project Info

Project
Annual EdWeb Upgrade
Code
WPS001
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
19-Aug-2019
Planning Date
16-Sep-2019
Delivery Date
29-Nov-2019
Close Date
17-Apr-2020
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation