Report for November 2019
- Report Date
- November 2019
Achievements in Last Period
- PHP upgrade completed on TEST
- UAT passed on TEST
- PHP upgrade completed on STAGING
- UAT passed on STAGING
Issues
- The LIVE upgrade scheduled for the end of November 2019 has been moved out to Thursday 12th December 2019 due to the change freeze in place because of strike action.
Next Steps
- Prep deployment to LIVE
- Deploy to LIVE
- Start to review user stories for next phase of the project
- Approved budget
- 100.0 days
- Activity this month
- 8.3 days
- Activity this year
- 27.5 days
- Activity to date
- 27.5 days
- Estimate to complete current year
- 62.5 days
- Estimate to complete future years
- 0.0 days