Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
- PHP upgrade successfully deployed to LIVE
- User stories progressed
Issues
- No issues to report
Next Steps
- Complete iteration planning
- User stories
- Estimations
- Iterations meetings
- Start Iteration 1
- Approved budget
- 100.0 days
- Activity this month
- 3.0 days
- Activity this year
- 31.5 days
- Activity to date
- 31.5 days
- Estimate to complete current year
- 62.5 days
- Estimate to complete future years
- 0.0 days