Report for December 2019

Report Date
December 2019

Achievements in Last Period

  • PHP upgrade successfully deployed to LIVE
  • User stories progressed

Issues

  • No issues to report

Next Steps 

  • Complete iteration planning
    • User stories
    • Estimations
    • Iterations meetings
  • Start Iteration 1 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
3.0 days
Activity this year
31.5 days
Activity to date
31.5 days
Estimate to complete current year
62.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual EdWeb Upgrade
Code
WPS001
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
19-Aug-2019
Planning Date
16-Sep-2019
Delivery Date
29-Nov-2019
Close Date
17-Apr-2020
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation