Organisation
Work/Task Breakdown
| Project Management | Project Services |
| Initiation | |
| Project Brief | Project Services |
| Planning | |
| Create Plan | Project Services |
| Impact analysis | Dev Tech |
| DEV | |
| POLO | |
| Upgrade DB/Migrate DB | Dev Tech |
| Support Upgrade/Interface Testing | Dev Tech |
| Support Upgrade | Development Team |
| Meetings | All |
| POLO TAD review | Dev Tech, All |
| TEST | |
| POLO | |
| Upgrade DB/Migrate DB | Dev Tech |
| Support Upgrade/Interface Testing | Dev Tech |
| Integration Testing with | Application Management - AH |
| Full UAT test with UWP | UWP |
| Support/Review Upgrade | Development Team |
| Deployment checklists for POLO | Application Management |
| ASOR POLO | All |
| LIVE | |
| POLO | |
| GO-LIVE Prep | Dev Tech |
| Upgrade DB/Migrate DB | Dev Tech |
| Support Upgrade/Interface Testing | Dev Tech |
| Take down and bring up Polopoly | Dev Tech |
| Support Post LIVE Testing | Application Management - AH |
| Support Go-LIVE | Development Team |
| Complete Operational Documentation | Dev Tech |
| Closure | |
| Technology Handover | Dev Tech, Tech Management, Application Management |
| DSOR | All |
| Project Close | Project Services |
Resources Skills and Cost
| IS Apps Section | Team | Estimate (Days) |
| Project Services | Project Services | 8.0 |
| Development Services | Development Team | 4.5 |
| Development Technology | 22.5 | |
| Production Management | Applications Management | 4.5 |
| Technology Management | 1.5 |
IS APPS Total 41 days
Estimated UWP Effort is 50 hours testing