Organisation

 

Work/Task Breakdown

Project Management Project Services
  
Initiation  
Project BriefProject Services
  
Planning  
Create PlanProject Services
Impact analysisDev Tech
DEV 
POLO 
Upgrade DB/Migrate DBDev Tech
Support Upgrade/Interface TestingDev Tech
Support UpgradeDevelopment Team
MeetingsAll
  
POLO TAD reviewDev Tech, All
  
TEST 
POLO    
Upgrade DB/Migrate DBDev Tech
Support Upgrade/Interface TestingDev Tech
Integration Testing with Application Management - AH
Full UAT test with UWPUWP
Support/Review UpgradeDevelopment Team
Deployment checklists for POLO Application Management 
ASOR POLO All
  
  
LIVE 
POLO 
GO-LIVE PrepDev Tech
Upgrade DB/Migrate DBDev Tech
Support Upgrade/Interface TestingDev Tech
Take down and bring up PolopolyDev Tech
Support Post LIVE Testing Application Management - AH
Support Go-LIVEDevelopment Team
Complete Operational DocumentationDev Tech
Closure 
Technology HandoverDev Tech, Tech Management, Application Management
DSORAll
Project CloseProject Services

Resources Skills and Cost

 

IS Apps SectionTeam Estimate (Days)
   
Project Services Project Services 8.0
   
Development ServicesDevelopment Team 4.5
   
   
   
 Development Technology 22.5
   
Production Management Applications Management 4.5
   
 Technology Management 1.5

IS APPS Total 41 days

Estimated UWP Effort is 50 hours testing

Project Info

Project
Polopoly Database Upgrade
Code
UWP008
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Withdrawn
Start Date
03-Oct-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Mar-2014
Overall Priority
Normal
Category
Compliance

Documentation

Plan