Organisation

Work/Task Breakdown

  • Requisition a new Virtual Machine (VM) for BETA (dust) ( IS)
  • Configure VM and install 3.10 version of Timetabler and components (IS)
  • Sign off BETA (pre-dev) environment prior to upgrade (TTU)
  • Upgrade BETA to version 3.11 (IS, Scientia)
  • Create implementation plan to be used in upgrade of DEv, TEST and LIVE environments and seek QA advice from Scientia on the correctness of this plan (IS, Scientia)
  • Carry out regression testing  on upgraded BETA environment (TTU)
  • Create a recommendation along with indicative timings for rolling out the upgrade (IS/TTU)
  • Upgrade Dev and complete peer review (IS)
  • Upgrade Test and complete acceptance review (IS/TTU)
  • Upgrade Live and complete deployment review (IS/TTU)
  • Upgrade relevant user documentation (TTU)
  • Upgrade Train and and accept (IS/TTU)

 

Resources Skills and Cost

The majority of effort on this project is likely to come from Development Technology and the Timetabling Unit.  

Scientia will be engaged for one day's consultancy effort at a cost of £1000 per day. The business will pay this cost.

Development Team time is only likely to be required as a consequence of the upgrade causing existing configuration or University developed components to fail.  This must be reviewed as part of the recommendation.

 

Project Info

Project
Timetabling Scientia Upgrade
Code
TTU009
Programme
Timetabling (TTU)
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
28-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jun-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation

Plan