TEL034: Lynda.com Implmentation: BI/BO POC to LIVE
- Report Date
- December 2016
Achievements this period
Implementation Plan complete
OLA complete
JH 1:1 training completed
Issues
https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/40
Next Steps
Integration completed
Peer testing complete
Test available
UAT completed and signed off
Deployment Checklist completed
Handover/Deploy
Closure report completed/signed off
Project closed
Milestones
Target date |
Title |
Complete |
13/05/16 |
Planning |
YES |
11/01/17 (13/12/16) |
Delivery |
NO |
31/01/17 (22/12/16) |
Closure |
NO |
- Approved budget
- 109.0 days
- Activity this month
- 7.0 days
- Activity this year
- 59.0 days
- Activity to date
- 98.5 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days