TEL034: Lynda.com Implementation
- Report Date
- November 2016
Achievements this period
None
Issues
https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/38
Next Steps
Integration completed
Peer testing complete
Test available
1:1 training/UAT completed and signed off
Deployment Checklist completed
OLA reviewed and signed off
Handover/Deploy
Closure report completed/signed off
Project closed
Milestones
Target date |
Title |
Complete |
13/05/16 |
Planning |
YES |
13/12/16 |
Delivery |
NO |
22/12/16 |
Closure |
NO |
- Approved budget
- 104.0 days
- Activity this month
- 5.0 days
- Activity this year
- 51.5 days
- Activity to date
- 90.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days