TEL034: Lynda.com Implementation: October
- Report Date
- October 2016
Achievements this period
System design complete
System build commenced
All base flat format replicated Lynda reports created
Universe written
Issues
Resource contract not extended
https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/24
POC UAT not undertaken in time for build commence as planned
https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/25
Next Steps
Business to UAT POC BI reporting and provide decission on deliverable
Build complete
Milestones
Target date |
Title |
Complete |
13/05/16 |
Planning |
YES |
18/11/16 |
Delivery |
NO |
08/12/16 |
Closure |
NO |
- Approved budget
- 104.0 days
- Activity this month
- 17.5 days
- Activity this year
- 50.0 days
- Activity to date
- 90.0 days
- Estimate to complete current year
- 13.5 days
- Estimate to complete future years
- 0.0 days