TEL034: Lynda.com Implementation: October

Report Date
October 2016

Achievements this period

System design complete

System build commenced

All base flat format replicated Lynda reports created

Universe written

Issues

Resource contract not extended

https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/24

POC UAT not undertaken in time for build commence as planned

https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/25

Next Steps

Business to UAT POC BI reporting and provide decission on deliverable

Build complete

Milestones

Target date

Title

Complete

13/05/16

Planning

YES

18/11/16

Delivery

NO

08/12/16

Closure

NO

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
GREEN
RAG Commentary
https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/25
Change Status
Activity
Approved budget
104.0 days
Activity this month
17.5 days
Activity this year
50.0 days
Activity to date
90.0 days
Estimate to complete current year
13.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Lynda.com Implementation
Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
18-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-May-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary