TEL034: Lynda.com Implementation

Report Date
August 2016

Achievements this period

Data Archiving process agreed and drafted

Presentation to SMT

LEARN andMoodle integration showcased

POC SDS reviewed and signed off

Issues

Delays in decision making to scope and sign off of BRD

https://www.projects.ed.ac.uk/project/tel034/issues/27

Project Re-Plan - Remaining Deliverables

https://www.projects.ed.ac.uk/project/tel034/issues/30

Business Lead Annual Leave

https://www.projects.ed.ac.uk/project/tel034/issues/31

 

Next Steps

Agree revised milestones for remaining deliverables

Agree resource requirements to deliver remaining milestones

Milestones

Target date

Title

Complete

13/05/16

Planning

YES

24/11/16

Delivery

NO

25/11/16

Closure

NO

Project Status
RAG Status
Time
RED
Cost
RED
Scope
AMBER
Overall
RED
Change Status
Activity
Approved budget
64.0 days
Activity this month
27.5 days
Activity this year
27.5 days
Activity to date
67.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Lynda.com Implementation
Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
18-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-May-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary