June 2016
- Report Date
- June 2016
Achievements this period - SOFT LAUNCH
Build complete
- Single sign on
- Lynda.com Implementation Plan
- Test scripts drafted
- Digital Skills & Training Website landing page created
Integration complete
- ECA UUN's matched
- IDP's reconfigured
UAT Complete
- Undertaken succesfully and earlier than planned
- Handover to LIVE
GO LIVE
Comms
Issues
Insufficient Project Services Delivery Support days to deliver Full Launch
https://www.projects.ed.ac.uk/project/tel034/issues/23
Next Steps - FULL LAUNCH
Business Requirements defined
System Design Work Packages defined
- Single Sign On configuration
- Install of Learn
- Install of Moodle
- MyEd - added value functionality de scoped
- VRS - defined
- Business Objects - reporting meaningful BI
- TAD Signed Off
System Build Work Packages
Milestones - SOFT LAUNCH
Target date | Title | Complete |
13/05/16 | Planning | YES |
16/06/16 | Delivery | YES |
Milestones - FULL LAUNCH
Target date | Title | Complete |
13/05/16 | Planning | YES |
23/08/16 | Delivery | NO |
14/09/16 | CLOSE | NO |
- Approved budget
- 49.0 days
- Activity this month
- 12.4 days
- Activity this year
- 29.5 days
- Activity to date
- 17.1 days
- Estimate to complete current year
- 9.3 days
- Estimate to complete future years
- 10.0 days