June 2016

Report Date
June 2016

Achievements this period - SOFT LAUNCH

Build complete 

  • Single sign on
  • Lynda.com Implementation Plan
  • Test scripts drafted
  • Digital Skills & Training Website landing page created

Integration complete

  • ECA UUN's matched
  • IDP's reconfigured

UAT Complete

  • Undertaken succesfully and earlier than planned
  • Handover to LIVE

GO LIVE

Comms

Issues

Insufficient Project Services Delivery Support days to deliver Full Launch

https://www.projects.ed.ac.uk/project/tel034/issues/23

Next Steps - FULL LAUNCH

Business Requirements defined

System Design Work Packages defined

  • Single Sign On configuration
  • Install of Learn
  • Install of Moodle
  • MyEd - added value functionality de scoped
  • VRS - defined
  • Business Objects - reporting meaningful BI
  • TAD Signed Off

System Build Work Packages

Milestones - SOFT LAUNCH

Target date

Title

Complete

13/05/16

Planning

YES

16/06/16

Delivery

YES

 

Milestones - FULL LAUNCH

Target date

Title

Complete

13/05/16

Planning

YES

23/08/16

Delivery

NO

14/09/16CLOSENO
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
49.0 days
Activity this month
12.4 days
Activity this year
29.5 days
Activity to date
17.1 days
Estimate to complete current year
9.3 days
Estimate to complete future years
10.0 days

Project Info

Project
Lynda.com Implementation
Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
18-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-May-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary