Report for April 2017
- Report Date
- April 2017
Achievements this period
- Deployment to test completed
- Reporting testing completed by business resource
- Deployment of code to Live environment completed
- Additional business users set up on live
- Review of live reports underway
Issues
- PICCL raised and approved to extend milestone for delivery and closure, dates agreed by Project Team
Next Steps
- Guidance document to be completed
- Review of live reports confirmed, expected 1st May
- Project closure meeting scheduled for 3rd May
- Closure approval
The project status is GREEN.
Target date |
Title |
Complete |
03/05/17 |
Closure |
In progress |
- Approved budget
- 132.0 days
- Activity this month
- 5.3 days
- Activity this year
- 84.5 days
- Activity to date
- 124.4 days
- Estimate to complete current year
- 1.1 days
- Estimate to complete future years
- 0.0 days