Report for April 2017

Report Date
April 2017

Achievements this period

  • Deployment to test completed
  • Reporting testing completed by business resource
  • Deployment of code to Live environment completed
  • Additional business users set up on live
  • Review of live reports underway

Issues

  • PICCL raised and approved to extend milestone for delivery and closure, dates agreed by Project Team

Next Steps

  • Guidance document to be completed
  • Review of live reports confirmed, expected 1st May
  • Project closure meeting scheduled for 3rd May
  • Closure approval

 

The project status is GREEN.

 

Target date

Title

Complete

03/05/17

Closure

 In progress

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
132.0 days
Activity this month
5.3 days
Activity this year
84.5 days
Activity to date
124.4 days
Estimate to complete current year
1.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Lynda.com Implementation
Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
18-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-May-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary