Report for March 2017

Report Date
March 2017

Achievements this period

  • 3rd iteration of UAT now completed and all JIRAs now resolved / closed
  • Closure report completed and ready for sign off once deployed to test and live
  • Project handover to other Project Manager to complete closure activities due to departure of current PM
  • Deployment of code to test environment in progress

Issues

  • During handover of code to support it was noted that there was millions of records in the database, following investigation this has now been resolved and checked against the daily file
  • Once test deployment has complete we will need business resource to check reporting before agreeing to deploy to Live they are currently on annual leave until 10th April revised milestones will have to  be agreed

Next Steps

  • Handover/Deploy
  • Deployment Checklist completed
  • Project closed

 

The project status is AMBER due to the delay in resolution of JIRAs and unavailability of business lead to check reporting once deployed in Test, milestones to be revised.

Milestones (tbc)

Target date

Title

Complete

31/03/17

Delivery

NO

28/04/17

Closure

NO

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE : Resolution of JIRAs and Testing to confirm accuracy of reporting delayed deployment to test, this is now underway however milestones now require to be revised as Business Lead on annual leave early April and the project will require their time to check reporting in Test environment.
Change Status
Activity
Approved budget
132.0 days
Activity this month
6.5 days
Activity this year
78.5 days
Activity to date
118.4 days
Estimate to complete current year
1.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Lynda.com Implementation
Code
TEL034
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
18-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
19-May-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary