Report for February 2017
- Report Date
- February 2017
Achievements this period
1st iteration of UAT completed - fixes implemented
2nd iteration of UAT completed - fixes implmented
Issues
Resource Conflict
https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/29
Business Lead availability to complete UAT and address outstanding JIRA's
https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/42
Next Steps
Review/revise milestones to reflect extended UAT
3rd iteration of UAT completed - ASOR
Deployment Checklist completed
Handover/Deploy
Closure report completed - DSOR
Project closed
Milestones
Target date |
Title |
Complete |
13/05/16 |
Planning |
YES |
01/03/17 (11/01/17) |
Delivery |
NO |
08/03/17 (31/01/17) |
Closure |
NO |
- Approved budget
- 109.0 days
- Activity this month
- 5.0 days
- Activity this year
- 71.0 days
- Activity to date
- 110.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days