TEL034: Lynda.com Implementation
- Report Date
- April 2016
Achievements this period
An initial meeting with Jenni to introduce myself and have a quick review of the project objectives.
Initial convo's with Dev Tech regarding resource challenges
HR stakeholders identified
Initial convo's regarding Single Sign On
Project Plan drafted
3 Point Estimate drafted
Project Brief issued for sign off but withdrawn and extention to planning Phase from 29/04 to 13/05
Issues
Planning dealys due to unidentified Business Scope
Lynda.com ownership and administration
Next Steps
Business Requirements Document
System Design
Clarification of integration with LEARN and Moodle
Milestones
Target date | Previous Date | Title | Complete |
13/05/16 | 29/04/16 | Planning | NO |
18/07/16 | 18/07/16 | Delivery | NO |
01/08/16 | 01/08/16 | Closure | NO |
- Approved budget
- 25.0 days
- Activity this month
- 2.4 days
- Activity this year
- 2.4 days
- Activity to date
- 2.4 days
- Estimate to complete current year
- 22.1 days
- Estimate to complete future years
- 0.0 days