Organisation

Work/Task Breakdown

This project comprises a set of issues raised in jira grouped into two work packages for resolution and deployment: WP1 Priority JIRA’s, system outputs and exports, and WP2 Admin system changes and improvements. Details of the jiras requested and prioritised are listed in the Business Requirements summary.

Resources Skills and Cost

TeamDays
Project Services25.5
Software Development53.0
Development Technology3.0
Applications Management5.0
Directors Office1.5
Total Days88.0

Please see 3 point estimate for further detail.

Project Info

Project
CAM - Enhancements to UG and PG Degree Finders
Code
STU251
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
04-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary