Organisation
Work/Task Breakdown
This will be a two-phase project, with the PG Application updates being developed in the first phase, and the UG Application updates in the second. They will deploy on different dates.
The detail of the tasks is in the 3 point estimate at the end of planning linked below.
Resources Skills and Cost
| Team | Estimate (d) |
| Project Services | 17.5 |
| Software Development | 49 |
| Development Technology | 10 |
| Applications Management | 14 |
| Directors Office | 1.5 |
| 92 |
Please see the 3 point estimate for further detail.