Estimate version 2.0
This is the updated estimate produced for WIS meeting on 11th April.
Project Management | Project Manager | 15 days | |
Quality Assurance | IS Apps | 2 days | |
Planning | Planning | Project Services | 2 days |
Business Analysis | Business Analysis for Radium | Business Analyst | 6 days |
Remaining tasks for Phase 1 SQL/ Coldfusion Upgrade | Support Testing on DEV | Development Services - Development Technolog, Production Management Application Management | 4 days |
Migrate to LIVE | Development Services - Development Technolog, Production Management Application Management | 3 days | |
Deploy to LIVE and support any issues | Development Services - Development Technolog, Production Management Application Management | 3 days | |
Waiting List Enhancements (changes for 2 lists), DSA Process Improvements | Work for KELSO system that has been signed off in the Business Requirements Document | ||
Systems Design | Systems Design | Development Services | 2 days |
Waiting List modicifcations | Development Services | 32 days | |
Peer Testing | Development Services | 2 days | |
System Documentation | Production Management - Applications Management | 1 day | |
Implementation Plan | Development Services - Development and Configuration Team | 2 days | |
Radium Enhancements | |||
Business Analysis | |||
Systems Design | Systems Design | Development Services | 3 days |
Radium Enhancements | Development Services | 13 days | |
Peer Testing | Development Services | 1 days | |
System Documentation | Production Management - Applications Management | 1 days | |
Implementation Plan | Development Services - Development and Configuration Team | 2 days | |
Total Revised Estimate for work remaining | 94 days | ||
Overall Proposed Approved Budget | 259 days |
Attachment | Size |
---|---|
![]() | 60 KB |