Impact

 

Priority and Funding

This project has been classed as priority 2 (High).

The project funding of 190 IS Apps days is from the Student Services programme budget.  The estimation for the mandatory requirements will be confirmed following User Stories Workshops.

 

Impact and Dependencies

As this is a new online IT tool which is being developed, there is no impact from other projects.

There are no known dependencies. 

 

Project Info

Project
External Examiner Online Reporting System
Code
STU235
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Tina Harrison
Current Stage
Close
Status
Closed
Start Date
04-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
7
Overall Priority
Higher
Category
Compliance