Build Test Summary

Open JIRA Issues (including any outstanding DEV Environment Issues)

 

STU234-18 and STU234-20 are unresolved at the time of PPBR.  Both of these are infrastructure issues, not issues with the software itself.  At this point in time the problem is only in Dev, and there has been no concern that this is a result of repointing to CF9, so shouldn't stop UAT.  

Project Info

Project
Upgrade SAGE to CF9
Code
STU234
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Steve Norman
Current Stage
Close
Status
Closed
Start Date
07-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Apr-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance