PUBS Database Upgrade
PUBS Database Upgrade
Home
Projects
PUBS Database Upgrade
Implementation Tasks
Implementation Tasks
Infrastructure Components
Application Components
Application Setup
Integration Components
Data Population
Data Migration
Implementation Validation
Outline
PUBS Database Upgrade
Implementation Plan
26/2/13 Meeting With New Sponsor
14/11/12 Team Meeting
Project Brief
Overview
Impact
Organisation
Implementation Tasks
Completion Report
Rollout Steps
‹ Organisation
up
Completion Report ›
This article was published on
Oct 18, 2016
Project Info
Project
PUBS Database Upgrade
Code
STU224
Programme
Student Services (STU)
Project Manager
Morna Findlay
Project Sponsor
Sara Cranston
Current Stage
Close
Status
Closed
Start Date
17-Apr-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-May-2013
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Initiate
No documents
Plan
Project Brief
Execute
Implementation Plan
Implementation Tasks
Rollout Steps
Deliver
No documents
Close
Completion Report
Other
26/2/13 Meeting With New Sponsor
14/11/12 Team Meeting