Report for October 14

Report Date
October 2014

Achievements in Last Period

  •  Project closed 28 October 14

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
58.0 days
Activity this month
2.5 days
Activity this year
16.0 days
Activity to date
58.8 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Update IS Alerts Page (SMI004)
Code
SMI004
Programme
ISG - IT Service Management (SMI)
Project Manager
Sue Woodger
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
25-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Oct-2014
Category
Discretionary