The project covers preparatory work for the new core system, focussing around getting confirmation during fit/gap sessions with the vendor that the assumptions and statement of needs etc. covered by FTP001, FTP002 and FTP008 are all achievable with the new core system.  The detailed design sessions, which will come later in 2019, will expand on the these documents and add the detail required for implementation.

  • Where assumptions/statement of needs are not achievable investigate the potential issues this causes.
  • Identify any potential 'benefits' from the OBC that may not be fulfilled.

 

Also investigating ‘areas still to be defined’ such as:

  • Internal Trading and inter-company transactions
  • The treatment of Research Overheads

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2019 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Finance Core Pre-requisites (FCPR)
Code
SEPFTP013
Programme
Service Excellence - Finance Transformation Programme (SEPFTP)
Management Office
Service Excellence PMO
Project Manager
James Mckay
Project Sponsor
Garry Robertson
Current Stage
Close
Status
Closed
Start Date
07-Jan-2019
Planning Date
31-Jan-2019
Delivery Date
30-Apr-2019
Close Date
10-May-2019
Overall Priority
Normal

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.