Project Brief

Document Sign Off

Name Project Role Date Signed Off
Victoria Dishon Project Sponsor 18-Jul-2019
Richard Bailey Project Manager (Project Team Member) 16-Jul-2019
Ben Armstrong Programme Manager / Senior Supplier 16-Jul-2019
Muriel Mewissen Portfolio Manager 16-Jul-2019
Duncan Colhoun Business Lead / IT Services Manager (Project Team Member) 18-Jul-2019
Shane Voss Super User / Computing Officer (Infrastructure Services) (Project Team Member) 18-Jul-2019
Chris Hill Super User / Database User Support Analyst (Project Team Member) 18-Jul-2019
Mark Lang Development Technology Team Manager 16-Jul-2019
Heather Larnach Production Management Lead  (Project Team Member) 17-Jul-2019
Anne Graham Applications Management Team Manager (Project Team Member) 17-Jul-2019
Stefan Kaempf Head of Production Management Covered by Heather / Anne from Production
Ewan Scott Database and Systems Administrator (Project Team Member)  

Date                   

Version      

Author                       

Section                     

Amendment                              

02/04/2019

Draft v0.1

Victoria Weinsberg

All

Initial draft for review / discussion 

08/07/2019 Draft v0.2 Richard Bailey All Updates after review by new Project Manager to prepare Brief for circulation / review by Stakeholders 
10/07/2019 Draft v0.3 Richard Bailey All Minor changes made after Programme Manager review, Draft circulated to Signatories for review / sign off.
15/07/2019 Draft v0.4 Richard Bailey All Further minor changes following on from a Project Team initiation meeting and recirculated to Signatories for review / sign off.
17/07/2019 Draft v0.5 Richard Bailey Background, Scope Minor change to the Background text to include an amend to licencing based on an email confirmation from Stefan received 21-Mar-2019 and the associated Scope item

Project Info

Project
GeoSciences Databases Upgrade and Migration
Code
SCE015
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Victoria Dishon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
29-Mar-2019
Planning Date
19-Jul-2019
Delivery Date
11-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary