June 2015
- Report Date
- June 2015
Achievements in Last Period
- Complete and agree project brief, with estimate, plan and milestones - complete
- Determine baseline values for current usage and costs - partially complete, baseline for 6 of the 10 of the scientific instruments in question determined
- Identify high-level requirements by role - complete
Issues
- None
Next Steps
- Draft business case outline and complete business case:
- Complete baseline financial and usage data (Jim)
- Complete identification of high-level requirements by role
- High-level review of existing systems to determine overlap
- High-level estimate of work needed if existing systems are not sufficient
Milestones
| 26-Jun-2015 | Establish baseline financial and usage data |
| 09-Jul-2015 | Complete Business Case |
| 24-Jul-2015 | Project Closure |
- Approved budget
- 5.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days