Report for November 2019
- Report Date
- November 2019
Achievements in Last Period
-
All pilots are now underway (except for PGAF which has been removed from scope - PICCL decision 17)
-
The following documents were presented to the Project Board for ratifying:
-
Post-pilot plan
-
Definition of study and work away
-
Glossary of study and work away terms
-
SWAY Service Catalogue
-
-
Grant Calculator Options Appraisal completed
Issues and Risks
- Risk that study and work away data not available for post pilot planning (risk 38)
-
Risk that grant calculator functionality requires significant effort to deliver (risk 39)
- Definition of study and work away not agreed (PICCL issue 16)
Next steps
- Start technical feasibility study for Grant Calculator recommended option
- Start data gathering within Discovery phase
- Consolidate pilot feedback
- Approved budget
- 1415.0 days
- Activity this month
- 69.2 days
- Activity this year
- 175.4 days
- Activity to date
- 175.4 days
- Estimate to complete current year
- 775.0 days
- Estimate to complete future years
- 0.0 days