Report for October 2019
- Report Date
- October 2019
Achievements in Last Period
-
LLC pilot started on 30th Oct
-
Business School pilot started on 4th Nov
-
Post-pilot planning has started
Issues
- Definition of study and work away not agreed (PICCL Issue 16)
Next steps
- Start pilots in remaining pilot Schools
- Confirm definition of study and work away
- Complete post pilot planning
- Approved budget
- 1415.0 days
- Activity this month
- 69.2 days
- Activity this year
- 175.4 days
- Activity to date
- 175.4 days
- Estimate to complete current year
- 775.0 days
- Estimate to complete future years
- 0.0 days