Report for October 2019

Report Date
October 2019

Achievements in Last Period

  • LLC pilot started on 30th Oct

  • Business School pilot started on 4th Nov

  • Post-pilot planning has started

Issues

Next steps

  • Start pilots in remaining pilot Schools
  • Confirm definition of study and work away
  • Complete post pilot planning
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Time is amber: post pilot planning is in progress and until this completes there is uncertainty about project milestones
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
Moderate
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
SA&S Programme Manager. SA&S Programme Lead.
Activity
Approved budget
1415.0 days
Activity this month
69.2 days
Activity this year
175.4 days
Activity to date
175.4 days
Estimate to complete current year
775.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Study and Work Away Implementation
Code
SAS016
Programme
Service Excellence - Student Administration and Support (SAS)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Chris Yeomans
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
30-Oct-2018
Planning Date
29-Mar-2019
Delivery Date
31-Jul-2020
Close Date
07-Aug-2020
Programme Priority
1
Overall Priority
Higher
Category
Discretionary