Overview

Background

A new subject coding system - the Higher Education Classification of Subjects (HECoS) - has been developed to replace the Joint Academic Coding System(JACS)  currently used for the HESA statutory returns  

JACS is used by HESA and UCAS to classify subjects of study; the implementation of HECoS provides an opportunity for a far broader range of stakeholders to use a common subject coding system in the future.

Unlike JACS, the subject code identifiers are randomly generated to avoid the coding frame running out of space and HECOS codes are non-hierarchical. JACS Subject codes are held at programme and course level in EUCLID and HECOS codes will also need to be recorded at programme and course level.  Background to this project and a mapping of JACS to HECoS codes can be found at https://www.hesa.ac.uk/innovation/hecos.

There is no direct mapping between JACS and HECOS codes.  Whilst some JACS codes have a 1:1 relationship with HECOS codes it should not be assumed that this is universal.  Some element of human decision making is therefore required to decide the correct HECoS code to apply at programme and course level.  Before this project was initiated Governance and Strategic Planning (GaSP) ran an exercise in consultation with School s to recode University of Edinburgh programmes and the Student Analytics and Insights team coded University of Edinburgh courses using the new coding framework.

The new HECoS codes are also used in the UCAS Collection System.  The work on the recoding of UCAS has been completed.  GaSP are already working on the recoding to pass this to SRA and Admissions Offices.  Scholarships and Student Funding have been manually input HECoS codes into the SLC HEI Database to support student loan applications. Also impact on UKVI / T4 requirements.

 

Scope

The aim of this project is the conversion of JACS to HECoS codes in the student record (EUCLID) and its downstream systems to support the production of the HESA return.  It is a statutory requirement that HECOS codes be returned to HESA in the 2019/20 Student return.

Not in Scope:

  • The analysis & implementation of the HECoS changes across student systems was done earlier. It informed the scope of work of this project, resources and effort.
  • It does not include the implementation for other areas that have been done under SAC066 (closure report https://secure.projects.ed.ac.uk/project/sac066/closurereport)

Objectives, Deliverables, Benefits, Success Criteria

This project has 2 objectives:

Objectives

Deliverables

Benefits

Success Criteria

Priority  Owner

O1-Complete conversion to HECoS

D1-Agree recoding structure for programme and subject codes

D2-Convert all JACS codes in the student record incl programmes with missing codes

Support the production of the return

Valid codes for use across student systems

  • Deadline is met for the next statutory return. Student Data team needs the new code to start validating the data from Feb to meet their deadline
  • The subject codes are correct and can be used by GaSP and the Student Data team

O1 Must

D1 , 2 Must

 

Brenda Kutereba

O2-Update processes, reports and downstream feeds where JACS codes are currently used

Implement system changes

D3-in the student record,

D4- in the reporting BI universes,

D5 -in the downstream feeds and

D6 - in the ‘IS programme’ used to produce the current statutory return

Support the production of the HESA return

Service continuity once conversion made

  • Deadline is met for the next statutory return
  • No impact to BAU service: no bugs are reported post live

 

O2 Must

D3, 4, 5, 6 Must

Edmnund Farrow

Project Milestones

Stage Milestone Due Date
Plan End of planning 18-Nov-2019
Analyse Analysis of the coding structure and recoding tasks 29-Nov-2019
Execute Conversion to HECoS in Dev 20-Dec-2019
Build System changes made in Dev (depends on conversion in Dev) 17-Jan-2020
Execute Conversion to HECoS in Test 24-Jan-2020
Integrate Function test the system changes in Test (depends on conversion in Test) 29-Jan-2020
Execute Conversion to HECoS in TRN 03-Feb-2020
Accept Deploy system changes in TRN (depends on conversion in TRN) 03-Feb-2020
Deliver Conversion to HECoS in Live 05-Feb-2020
Deliver Deploy system changes in Live (depends on conversion in Live) 05-Feb-2020
Deliver Deployment sign off review DSOR 19-Feb-2020
Close Close 04-Mar-2020

Project Info

Project
Implementation to HECoS codes
Code
SAC082
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Paula Webster
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
23-Sep-2019
Planning Date
28-Oct-2019
Delivery Date
05-Feb-2020
Close Date
04-Mar-2020
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation

Plan