Report for December 2019
- Report Date
- December 2019
Achievements this period
- Project has been re-planned to take account of the impact of the industrial actions
- SAC083 the SITS Double Software Upgrade will now take place before the SAC080 SITS RedHat Operating System move to Centos
- Project will restart in mid February with TEST assuming that the SITS upgrade is being progressed and signed off in TEST
- ASTA planning has been amended to agree with the amended milestones
- TAD was provided by Dev Tech to Tech Management
- ITI have delivered the LIVE Servers
- The project sponsor has approved the revised dates - 7-Jan-2020
Issues
- Project will now be suspended
Next Steps
- Set up a project meeting before end of February
- Suspend project in January
- Unsuspend project in mid February
- TEST environment upgraded, signed off and on new servers by 24-Feb-2020
- TRN environment upgraded, signed off and on new servers by 9-Mar-2020
- LIVE environment upgraded, signed off and on new servers by 23-Mar-2020
- DUST environment upgraded, signed off and on new servers by 06-Apr-2020
- The other milestones can be found in the milestone log below
| Stage | Milestone | Due Date |
|---|---|---|
| Integrate | TEST Environment Upgraded, Signed Off and on new servers | 24-Feb-2020 |
| Accept | TRN Environment Upgraded, Signed Off and on new servers | 09-Mar-2020 |
| Deliver | LIVE Environment Upgraded, Signed Off and on new servers | 23-Mar-2020 |
| Deliver | DUST Environment Upgraded, Signed Off and on new servers | 06-Apr-2020 |
| Deliver | Deployment Sign off | 13-Apr-2020 |
| Close | Decommissioning of all Environments | 20-Apr-2020 |
| Close | Closure | 11-May-2020 |
- Approved budget
- 105.0 days
- Activity this month
- 3.0 days
- Activity this year
- 54.0 days
- Activity to date
- 67.0 days
- Estimate to complete current year
- 35.0 days
- Estimate to complete future years
- 0.0 days