Organisation

Work/Task Breakdown

The following steps will be followed for each improvement:

1.     Identify improvement

2.     Document requirements with the business, to include business and system changes.  Record in JIRA.

3.     Produce a prioritised list of system changes with estimates.  Record in JIRA.

4.     Define iteration/release cycle

5.     Define and prepare training requirements where required

6.     Plan release(s) to the live environment. Record as an acceptance/delivery milestone to include acceptance sign off from main stakeholders involved (business analyst, developer, business owner, Student Systems Support, IS Apps Man) .

7.     Track the improvement's achievements, issues, and next steps on the monthly project report.

 

Resources Skills and Cost

The resources and skills required will be dependent on the content of each of the improvements.

An IS-APPS budget of 350 days has been allocated to cover this project. The budget allocation reflects the relevant importance given to continuous improvement work by the board and does not constitute an estimate for specific items of work.  The majority of the days are expected to be resourced from within the core SSP team, but IS Application Management/Development Technology will be required for promotion into the live environment.

There is equivalent Student Systems resource available to support business analysis, testing and training of each improvement

 

Project Info

Project
Continuous Improvements
Code
SAC043
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Karen Osterburg
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
03-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Oct-2016
Programme Priority
2
Category
Discretionary