Work/Task Breakdown
Task | Deliverable | Owner |
Project Management | Project authorisation, Brief and Project documents. Communication and coordination with stakeholders. | Franck Bergeret |
Build It | Existing Technical Architecture Document (TAD) update and reviewed | IS Dev Tech/Tech Man/ App Man |
Reconfigure DEV and move web tier functionality | IS Dev Tech/Config Team
| |
Peer test | IS Dev Tech/ Config Team | |
Implementation Plan | IS Dev Tech/ Config Team | |
Reconfigure TEST and move web tier functionality | IS Dev Tech
| |
Check It | Plan and prepare required tests (incl performance test) | IS Dev Tech / Config Team |
Review Tests | SACS | |
Test two Tier EUCLID in TEST | SACS, IS Dev Tech
| |
| ||
Document & handover | Update existing TAD (in https://www.wiki.ed.ac.uk/display/insite/EUCLID+-+tech+collaboration)
| IS Dev Tech/Tech Man/ App Man/Config Team |
Deploy | Reconfigure LIVE and move web tier functionality (incl TRN environment) | Dev Tech |
DR/Resilience test Check two Tier EUCLID in LIVE | IS Tech Man
IS Dev Tech/SACS & end users | |
Close It | Closure Review | Franck Bergeret |
Resources Skills and Cost
The project is to be approved based on an estimate of 51 days for IS Apps (and 4 days for SACS*)
Task | Days Allocation | Resource |
Project Management, Initiation, Planning, review, communication | 10 days 1.8 day 2 days | Franck Bergeret Director office IS Dev Tech |
Design Review | 1 day 1 day | IS Dev Tech IS App Man, Tech Man |
Build: configure Dev and check Support/peer test Implementation Plan | 5.1 days 1.5 day 1.5 day |
IS Dev Tech IS Config team IS Dev Tech/Config Team
|
Integration: configure test and check test Test scenarios Review Test scenarios | 4.6 days 3.2 days 1 day 1 day | IS Dev Tech IS App Man Config Team SACS* |
Acceptance: handover support Test EUCLID | 3.2 Days 0.5 day 2 days | IS Tech Man/ App Man/ Dev Tech Config Team SACS* |
Deployment : Configure Live and Trn DR/Resilience Post Live checks |
5.4 days 2.7 days 1 day
| IS Dev Tech IS Tech Man SACS* |
Closure
Contingency, unplanned tasks, meetings, reviews |
2 days 0.5 day
4 days | Franck Bergeret IS Dev Tech |