Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for January 2020 January 2020 GREEN GREEN GREEN GREEN No Change
Report for December 2019 December 2019 GREEN GREEN GREEN GREEN No Change
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN No Change
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN No Change
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Datasync Refresh
Code
RSS206
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Analyse
Status
In Progress
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
04-Oct-2019
Delivery Date
30-Apr-2020
Close Date
29-May-2020
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation