Report for November 2019

Report Date
November 2019

Achievements in Last Period

  • Project Delivery pushed out due to Resource availability to conduct Subversion Upgrade now in Apr
  • 3rd Party have successfully completed testing in DEV; although upgrade took over 25hrs to complete
  • Changed DataSync Upgrade date due to Time it takes to upgrade, Resource availability and Strike Action
  • Re-planned to 8-11 Dec 19
  • Updated all Project Documents, sites and plans accordingly
  • Updated IS Alert and CR paperwork
  • Project Brief Completed, issued for approval

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • Project Delivery - Due to lack of Resources/BAU

Next Steps

  • Upgrade DataSync now 8-11 Dec 19 
  • Hold 1x Session 3rd party walk through RSS SVN to give a better understanding for 3rd Party/Quote
  • Decide on  SVN SME/3rd Party
  • Obtain SVN Detailed Quote
  • Obtain SVN Usage Feedback to enable a decision to be made
  • Decision to if Upgrade SVN or Retire
  • Plan SVN Upgrade or Retirement

Future Milestones

Full Milestone Table as fist time reporting full plan

**********SVN Detailed Planning Still to take place Dates TBC**********

Mile

Stone

Task Name

% Complete

Start

Finish

1

  Start Date for Project

100

02/09/19

02/09/19

2

  Project Documentation/Website/SharePoint  Updating

100

02/09/19

06/09/19

3

  Outline Requirements Sign Off

100

02/09/19

13/09/19

4

  DataSync Stakeholder and Vendor Engagement

100

02/09/19

27/09/19

5

  Project Planning

100

30/09/19

04/10/19

6

  Project Brief produced and Signed Off

98

18/11/19

22/11/19

7

  IS Alert and Go-CAB for DataSync Upgrade Completed 

100

25/10/19

29/10/19

8

  RSS Systems Team Builds DataSync DEV 

100

01/10/19

01/11/19

9

  owncloud Development on DataSync DEV

100

04/11/19

08/11/19

10

  owncloud Test DataSync DEV

100

11/11/19

15/11/19

11

  DataSync Upgrade on PROD and Test

0

08/12/19 

11/12/19

12

  Subversion Stakeholder and Vendor Engagement

0

04/11/19

27/03/20

13

  Subversion Retirement Decision

0

06/01/20

31/01/20

14

  IS Alert and Go-CAB for Subversion Upgrade Completed

0

31/03/20

07/04/20

15

  RSS Systems Team Builds Subversion DEV

0

31/03/20

10/04/20

16

  Vender Development on DEV

0

13/04/20

17/04/20

17

  Vender Test Subversion DEV

0

20/04/20

24/04/20

18

  Subversion Upgrade on PROD and Test

0

28/04/20

30/04/20

19

  Delivery Complete

0

28/04/20

30/04/20

20

  Acceptance

0

01/05/20

08/05/20

21

  Closure Project

0

11/05/19

29/05/19

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
5.7 days
Activity this year
11.3 days
Activity to date
11.3 days
Estimate to complete current year
63.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Datasync Refresh
Code
RSS206
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Analyse
Status
In Progress
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
04-Oct-2019
Delivery Date
30-Apr-2020
Close Date
29-May-2020
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation