Overview
Background
Worktribe, the company responsible for producing the University’s pre-award/post-award research administration management system, releases 2 major versions of the application per year.
There is a requirement to keep within touching distance of the latest version in order that the University is able to take advantage of functionality which relates to key University business processes, e.g. leveraging performance and functional improvements, legislative changes, and increasing demand from research funders and our own researchers.
It is envisaged that the University will never be any more than one major release behind Worktribe’s schedule.
The scope of this project is to upgrade the University’s installation of Worktribe to v3.1 ensuring that it continues to operate as expected including:
- Testing of processes adopted by the University
- Testing of the interfaces presenting data to Worktribe from Finance, HR, and IDM
- Testing of the outgoing interfaces between Finance and Worktribe
- Testing of the external reporting solution (and the Worktribe BI Extract)
- Testing of additional and/or enhanced functionality to the system
- Modifying the single sign-on mechanism to use Shibboleth instead of Cosign
- Upgrading WIKI pages and/or User Guidance
Once this upgrade has completed the supplier will commence auto patching on a monthly basis.
Scope
The scope of this project includes the following:
- Upgrading all three environments (DEV, TEST and LIVE) to version 3.1 of Worktribe
- Testing of processes adopted by the University
- Testing of the interfaces presenting data to Worktribe from Finance, HR, and IDM
- Testing of the outgoing interfaces between Finance and Worktribe
- Testing of the external reporting solution (and the Worktribe BI Extract)
- Testing of additional and/or enhanced functionality to the system - including the new automated patching functionality
- Modifying the single sign-on mechanism to use Shibboleth instead of Cosign
- Upgrading WIKI pages and/or User Guidance
- Upgrading service test plans to encompass the changes engendered by the introduction of the automated patching functionality
Objectives & Deliverables
| No. | Description | MoSCoW | Owner |
| O1 | To apply the Worktribe v3.1 upgrade to all necessary environments (DEV, TEST and LIVE) | ||
| D1 | Upgrades of Worktribe to v3.1 in DEV, TEST and LIVE environments at the University of Edinburgh | Must | Worktribe |
| O2 | To fully test the version upgrade and how it is applied across our environments | ||
| D2 | Full tests of business processes adopted by the University on Worktribe application | Must | Project team |
| D3 | Testing of the interfaces presenting data to Worktribe from Finance, HR, and IDM | Must | Project team |
| D4 | Testing of the outgoing interfaces between Finance and Worktribe | Must | Project team |
| D5 | Tests of the external reporting solution (and the Worktribe BI Extract) | Must | Project team |
| D6 | Testing of additional and/or enhanced functionality to the system - in particular the new automated patching functionality | Must | Project team |
| O3 | To modify the way single sign-on is used to log into Worktribe at UoE | ||
| D7 | Establishing Shibboleth as the preferred mode of signing onto Worktribe | Should | Worktribe/Project team |
| O4 | To update any relevant user support pages in our Wiki and related guidance documentation | ||
| D8 | Updated versions of support materials | Must | Project team |
| D9 | Updated service test plans to encompass the changes engendered by the introduction of the automated patching functionality | Must | Project team |
Benefits
- Worktribe is updated to the latest version, ensuring that supplier support is maintained
- Security is improved by changing to Shibboleth
- The business community will benefit for the resolution of bug fixes and additional functionality provided in the latest version
Success Criteria
- Bug fixes resolved by upgrading to version 3.1
- The upgrade of the Worktribe application is completed successfully in line with the software road map lifecycle
Project Milestones
| Stage | Milestone | Due Date |
|---|---|---|
| Plan | Planning milestone | 16-Aug-2019 |
| Build | Build complete (DEV) | 12-Sep-2019 |
| Accept | Integration & Acceptance complete | 03-Oct-2019 |
| Deliver | Delivery | 10-Oct-2019 |
| Deliver | Delivery sign-off | 22-Oct-2019 |
| Close | Project closure | 31-Oct-2019 |