Organisation

Work/Task Breakdown

Task             

Who                                                                                                                           

Priority                  

When

WP1

Hannah Kingsland / Damon Querry / Craig Middlemass

S

31-July-2017

WP3

Resolved under RES058 - 172

S

04-April-2017

WP4

Hannah Kingsland / RSO

S

31-July- 2017

WP8

Dev Tech / Dev Services

S

31-July - 2017

 

Resources, Skills and Costs

Project resource required are as follows:

WP1: Project Services (also L&UC research Information Services) 2 days effort

WP3: Application Management / Dev Services / Project Services – COMPLETE (Actual Effort 5.5 days)

WP4: Project Services / Research Support Office (5 days)

WP8: Development Technology / Development Services / Project Services (5 days)*

* Agree with business team a limit on resource effort days, if not able to implement POC

 

Project Governance

  • Monthly Project Status reports
  • Monthly Programme Review meetings

 

Project Stakeholders

                                           Name                                  

                                                            Business Area                                               

                                                              Role                                                                 

Responsibilities

Dominic Tate

IS L&UC / Scholarly Communication / Research Support

Project Sponsor

Budget holder/ Accountable for delivering the project benefits

 

Craig Middlemass

IS L&UC

Business Lead – Worktribe & PURE

Operational service management for Worktribe Research Management and PURE

Damon Querry Research Information Systems Business Lead  Assistance with delivery of WP1

Hannah Kingsland

IS Apps

Project Manager

Project initiation / Initial project planning / Project delivery

Karen Stirling

IS Apps

RES Programme Manager

Project initiation / Initial project planning / RES programme delivery – managing competing priorities to deliver the highest priority projects that will deliver the most benefits / have the greatest impact on the Research Management space

Olga Malkovskaya

Research Information Systems

Research Information Systems Officer

Looks after Research Professional system

Peter Jackson

Development Technology

Technical Lead

Technical delivery / assistance on WP1 and WP8

TBC

Development Services

Developer PHP

Technical delivery / assistance on WP8

 

 

 

Project Info

Project
Research Information Management - Small Enhancements
Code
RES063
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Apr-2018
Programme Priority
6
Overall Priority
Normal
Category
Discretionary