This project will switch-off legacy Research Management systems - Infinite and InfoEd and associated databases and interfaces- and then ITI will decommission the associated servers that host these applications and databases , and physically remove the old servers. ( as this old hardware is no longer covered by standard support). Associated software and staging tables will also need to be removed from some of the UoE shared infrastructure.

The implementation and rollout of the new Worktribe Research management system means that the InfoEd and Infinite systems are no longer required from June 2016 ,  and as  legacy data from 1st Jan 2008 has already been  migrated to the the new Worktribe system, then the legacy systems can be safely decommissioned.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2016 BLUE 25.0 days 5.0 days 0.0

Project Info

Project
Decommission InfoEd & Infinite
Code
RES061
Programme
Z. Research (RES) (closed August 2017)
Management Office
ISG PMO
Project Manager
James Thin
Project Sponsor
Hamish Macandrew
Current Stage
Close
Status
Closed
Start Date
21-Mar-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Aug-2016
Programme Priority
1
Overall Priority
Higher
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.