Report for June 2016
- Report Date
- June 2016
Achievements this Period
- Project Board Meeting held 23/6/16
- Agreed that the legacy Infinite and InfoEd servers / H/W can now be decommissioned
- All checks requiring InfoEd access completed - InfoEd LIVE switched off
Issues
- None
Next Steps
- Project closure
- Approved budget
- 25.0 days
- Activity this month
- 0.3 days
- Activity this year
- 4.1 days
- Activity to date
- 4.1 days
- Estimate to complete current year
- 15.4 days
- Estimate to complete future years
- 0.0 days