The corporate applications servers reach end of life in 2015. The Oracle HR & Payroll application therefore needs to be moved to the replacement servers within 14/15.
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| November 2016 | BLUE | 200.0 days | 197.0 days | 0.0 |