Completion Report

Project Summary:

Analysis of Resource Usage:

Staff Usage Estimate: 1 days

Staff Usage Actual: 1 days

Staff Usage Variance: 0%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

.

Key Learning Points:

.

Outstanding issues:

.

Project Info

Project
Mail Directory Upgrade
Code
P0118
Project Manager
Graeme Wood
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Start Date
01-Oct-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jan-2017