Impact

Priority and Funding

The project priority is normal.

The project will be core funded via College Ring Fence allocation.

Impact and Dependencies

It is important that this project is concluded by the end of July for the following reasons:

  • The teaching of Vet School Graduate Entry Programme  Year 1 starts on 5th August 2019: this is likely to increasingly be the focus for relevant Vet School staff.
  • This analysis and recommendation project needs to be complete to allow time for a future project which may involve a procurement and full business implementation before the deadline for accreditation. This must include potentially significant time to manually key in data and to complete the mapping against the criterion set by the external accrediting bodies (of which there are multiple).

Project Risks

Ref Title Initial Risk       Current Risk       Status       Management Approach      Risk Owner
1 Availability of Subject Matter Experts AMBER GREEN Closed Reduce Susan Rhind
2 Single Solution for Two Co-Sponsors                  GREEN GREEN Open Retain Sheila Fraser
3 Funding for the gathering of requirements GREEN GREEN Open Reduce Sheila Fraser
4 Funding for options analysis GREEN GREEN Open Reduce Sheila Fraser
5 Project Resource GREEN GREEN Open Reduce Muriel Mewissen

 

Project Info

Project
CMVM Curriculum Mapping Tool - Requirements
Code
MVM133
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
17-Apr-2019
Planning Date
10-May-2019
Delivery Date
05-Aug-2019
Close Date
09-Aug-2019
Overall Priority
Normal
Category
Discretionary