April 2016
- Report Date
- April 2016
Achievements in the last period
- The equipment has in part been installed. The room in the Western General requires estates to assist and contractors are booked to complete that room at the end of May.
- The project team have agreed how we will handle the user accounts within Panopto.
- The PCs have been setup.
- Recording tests have taken place.
Issues
- It is a slower process than would be ideal, but the team is working as quickly as possible to equip the rooms.
Next steps
- Complete the support setup which entails choosing a local support champion. The support officers are looking at that now.
- Setup Learn which will be done by the DLAM team.
- Complete the installations.
- Start the pilot.
| 13-May-2016 | Pilot Launch |
| 27-May-2016 | Installation Complete |
| 22-Jul-2016 | Requirements Review |
| 29-Jul-2016 | Closure |
- Approved budget
- 12.0 days
- Activity this month
- 2.1 days
- Activity this year
- 8.1 days
- Activity to date
- 8.1 days
- Estimate to complete current year
- 3.9 days
- Estimate to complete future years
- 0.0 days