April 2016

Report Date
April 2016

Achievements in the last period

  • The equipment has in part been installed.  The room in the Western General requires estates to assist and contractors are booked to complete that room at the end of May.
  • The project team have agreed how we will handle the user accounts within Panopto.
  • The PCs have been setup.
  • Recording tests have taken place.

Issues

  • It is a slower process than would be ideal, but the team is working as quickly as possible to equip the rooms.

Next steps

  • Complete the support setup which entails choosing a local support champion.  The support officers are looking at that now.
  • Setup Learn which will be done by the DLAM team.
  • Complete the installations.
  • Start the pilot.

 

13-May-2016Pilot Launch
27-May-2016Installation Complete
22-Jul-2016Requirements Review
29-Jul-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
12.0 days
Activity this month
2.1 days
Activity this year
8.1 days
Activity to date
8.1 days
Estimate to complete current year
3.9 days
Estimate to complete future years
0.0 days

Project Info

Project
CMVM and LTW Lecture Capture Pilot
Code
MVM010
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Paul Clark
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Oct-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary