Project Status Reports

Title Report Date Time Cost Scope Overall Change
August 2015 August 2015 GREEN GREEN GREEN BLUE
Report for July 2015 July 2015 GREEN GREEN GREEN GREEN
Report for June 2015 June 2015 GREEN GREEN GREEN GREEN
May 2015 May 2015 GREEN GREEN GREEN GREEN

Project Info

Project
MVM Migration To EdWeb and Site Restructure
Code
MVM006
Programme
MVM Business Administration (MVMBUS)
Project Manager
Tim Gray
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
18-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Sep-2015
Programme Priority
2
Overall Priority
Normal
Category
Discretionary