Organisation
Work/Task Breakdown
End of March 2014 - Agree a Governance and Service Model
Mid-April - Services Assessed and categorised based on the Service Model Late April Re-estimation and Funding Confirmed Late April Establish and sign off migration plan Migrate simple hosting - end of October Migrate dedicated hosting - end of December Migrate complex applications - end of March 2015
Closure April 2015
Resources Skills and Cost
Analysis up to mid-April Apps effort Estimated at 20-250 days in 13/1 Service Management effort to support the analysis - 5 days Architecture - assist and support the analysis - 3-5 days MVM LTS team " " - 6-10 days USD " 2 - 3-5 days
Remainder of project 70 days in 13/14, 50 days in 14/15 for IS Applications (includign Service management). Other areas of IS to be determined.
Estimations
No three point estimate is possible until we have review the existing applications and websites on the MVM i/f. The project is capped at 150 days, and the first phase of the project itself is capped at 30 days, and will have as its outcome a new estimate of the budget needed to completed the project that needs confirmed by Project Sponsor and MVM Portfolio Owner.
Risks around the budget have been raised.