Organisation

 

Work/Task Breakdown

End of March 2014 - Agree a Governance and Service Model

Mid-April - Services Assessed and categorised based on the Service Model Late April Re-estimation and Funding Confirmed Late April Establish and sign off migration plan Migrate simple hosting - end of October Migrate dedicated hosting - end of December Migrate complex applications - end of March 2015

Closure April 2015

 

Resources Skills and Cost

Analysis up to mid-April Apps effort Estimated at 20-250 days in 13/1 Service Management effort to support the analysis - 5 days Architecture - assist and support the analysis - 3-5 days MVM LTS team  " " - 6-10 days USD " 2 - 3-5 days

Remainder of project 70 days in 13/14, 50 days in 14/15 for IS Applications (includign Service management). Other areas of IS to be determined.

Estimations

No three point estimate is possible until we have review the existing applications and websites on the MVM i/f. The project is capped at 150 days, and the first phase of the project itself is capped at 30 days, and will have as its outcome a new estimate of the budget needed to completed the project that needs confirmed by Project Sponsor and MVM Portfolio Owner.

Risks around the budget have been raised.

 

Project Info

Project
MVM LTS service transition to IS
Code
MVM002
Programme
MVM Learning and Teaching (MVMLAT)
Project Manager
Maurice Franceschi
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
29-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Apr-2016
Programme Priority
1
Overall Priority
Normal
Category
Discretionary