Report for May 2019

Report Date
May 2019

Achievements in Last Period

  • agreed with Matt a date to present dates to PMS
  • closed project  

Issues and Risks

  • none

Next Steps

  • none

Future Milestones

n/a

 

Budget

The budget for this project has been fully used.

 

iti031_university_calendar_-_budget.xlsx

 

Project Sponsor Commentary

None.

 

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
the service documentation will be reviewed. changed and finalised over Dec/Jan
Activity
Approved budget
18.5 days
Activity this month
5.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
0.1 days
Estimate to complete future years
0.0 days

Project Info

Project
University Calendar
Code
ITI031
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
12-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
21-May-2019
Close Date
28-May-2019
Overall Priority
Normal
Category
Discretionary

Documentation