Report for February 2019

Report Date
February 2019

Achievements in Last Period

  • analysis

Issues and Risks

  • none

Next Steps

  • analysis  

Future Milestones

Deliver Delivery 21-Jun-2019
Close Closure 12-Jul-2019

 

Budget

 

 

Project Sponsor Commentary

None.

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
the service documentation will be reviewed. changed and finalised over Dec/Jan
Activity
Approved budget
18.0 days
Activity this month
2.5 days
Activity this year
2.5 days
Activity to date
2.5 days
Estimate to complete current year
15.5 days
Estimate to complete future years
0.0 days

Project Info

Project
University Calendar
Code
ITI031
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
12-Nov-2018
Planning Date
31-Jan-2019
Delivery Date
21-May-2019
Close Date
28-May-2019
Overall Priority
Normal
Category
Discretionary

Documentation